14,400 kilometres, 53 days and 4 different ships: it took a few strokes of logistical genius to transport a mobile crane to its destination on Earth’s southernmost continent. This is how it all began.
It’s December, 21st 2017. Three days before the Christmas holiday, Schmidbauer, a system service provider of crane technologies, receives an order approval from the German Aerospace Centre (DLR): one Liebherr LTM 1040-2.1 mobile crane is to be transported to Antarctica to help redevelop a polar research station. ‘After that, it was a race against time’, recalls Minka St. James, who managed the Antarctica project at Schmidbauer. ‘The crane needed to be shipped within just two weeks, or else we would have lost a whole year.’ Options for transporting equipment to Antarctica are extremely limited. The last stage from the southern tip of Chile to the research station is only possible through a joint effort by the German Aerospace Centre and the Chilean military.
Another challenge came in the form of strict environmental regulations. Ships are not permitted to dock directly at the pier next to the research station to avoid disturbing the penguin population that lives on the island. Instead, they must offload their cargo onto pontoons, around two kilometres off the coast. However, these shallow floats, similar to rafts, can only carry loads of up to eight tonnes. So within the span of two weeks, Schmidbauer must not only deal with the challenge of transporting the crane to Antarctica, but also dismantle it into individual parts and then plan how to reassemble it on site once it arrives.
‘Despite the difficult conditions, it was clear to us that a delay was not an option’, explains Minka St. James. By the beginning of January, the crane’s individual parts were shipped out from Schmidbauer's headquarters in Gräfelfing near Munich.
The first stop on the cranes route was the Port of Hamburg. From there, the cargo passed through multiple legs on a journey across the North Atlantic, then along the western coast of South America, before reaching Antarctica.
Within three days, the LTM 1040-2.1 mobile crane is disassembled into individual parts for transport. Each part cannot exceed the weight limit of eight tonnes.
Securely packed, the crane’s individual parts are loaded onto trucks for the journey to the Port of Hamburg, where they are then transferred to the container ship the “Cartagena Express”.
The first leg of the journey on the freight ship takes 18 days. Along the route, the freighter calls in at the ports of Antwerp (Belgium), Caucedo (Dominican Republic), and Cartagena (Colombia), before crossing the Panama Canal.
It is one of the world’s most famous short-cuts. Spanning 82 kilometres, the Panama Canal connects the Atlantic and Pacific Oceans. The mobile crane makes its way across this busy waterway on board the “Cartagena Express”.
The crane’s parts change ships for the first time at the Port of Buenaventura in Colombia. The crane spends the next nine days on board the “Cornelius Maersk”, travelling along the western coast of South America for the second leg of its journey. Starting in Colombia, it sails past Ecuador and Peru until it reaches the Port of San Antonio in Chile. Here, it is loaded onto yet another freight ship.
After nine days, the crane reaches the southern tip of South America. The city of Punta Arenas in Chile and its port are known as the gateway to Antarctica. This is the final port of call for logistics routes operated by commercial freighters. The journey onwards to Antarctica will be a joint effort by the German Aerospace Centre and the Chilean military.
The Schmidbauer engineering team assembles in Punta Arenas. Workshop supervisor Michael Paul and his assistant Charlie Zöllner are responsible for assembling the crane once it arrives in Antarctica. Before continuing the journey on board a Chilean military vessel, they check to ensure the crane has made it through the first part of the journey without any damage.
The final leg of the journey to the research station is an unpredictable one. The Antarctic weather can deteriorate without much warning. Although the Chilean military vessel reaches the waters near the research station ahead of schedule, heavy ice floes make it difficult to load the crane onto the pontoons. Only after a few days, when the weather has improved, are the individual parts transported to the pier next to the research station.
Preparation is everything, especially during a mission to Antarctica. This fell onto the shoulders of workshop supervisor Michael Paul and his assistant Charlie Zöllner from Schmidbauer, who worked on the crane from when it was disassembled in Gräfelfing until it was reassembled in Antarctica. During the disassembly process in Germany, they were supported by Tobias Hunger, a customer service representative from the Liebherr plant in Ehingen.
Michael Paul: No, this was a brand-new experience for me. When a colleague first told me that we would be assembling the crane in Antarctica ourselves, I thought he was joking at first. A job in Antarctica is completely out of the ordinary and it takes a lot of preparation.
Charlie Zöllner: I doubt I will ever work on another job like that again in my lifetime. In 2017, I hadn’t even been working at Schmidbauer that long, and this was my first job abroad. That was definitely quite extraordinary.
Michael Paul: There was a lot of pressure to do things quickly because disassembling the crane wasn't the only thing we had to do. We also had to prepare and pack all the spare parts and tools we would need for the installation on site. Things also became quite stressful when we needed to have individual crane parts packed by a specialist company and when we had to receive a large delivery of spare parts from Liebherr. Because of the tight schedule, everyone had to work at maximum capacity.
Michael Paul: Disassembling a crane is by no means standard procedure. Plus, the individual parts all had to weigh under eight tonnes and had to fit within specific dimensions. So we worked very closely with Liebherr customer service whilst we were disassembling the crane.
Tobias Hunger: It’s our job to solve our customer’s problems while also working to a tight schedule. But even for us, this was an unusual challenge. We studied the crane's technical drawings and developed a disassembly plan. We had to improvise certain things during the disassembly process; for example, we had to prepare a new, smaller diesel tank for the engine in the crane's undercarriage. Normally, the diesel tank for the undercarriage is located in the superstructure, but that had to be removed to keep within the weight limits. It was imperative that the engine would function correctly whilst the crane was being assembled on site. As we were disassembling the crane, it was also important to consider how it would be reassembled in Antarctica. We wanted to make sure that we would be able to reassemble it in as few steps as possible under the harsh weather conditions there.
Michael Paul: We very quickly learned a local saying: ‘In Antarctica, the only certain thing is that nothing is certain.’ So for example, it took longer than expected to transfer the crane’s parts onto the pontoons because of all the ice floes floating off the coast of the island. Even just positioning the outrigger on the pontoon was very stressful because of its size. We had to guide the lifting work from a small motorboat. But to get down to the boat, we had to climb down a metal ladder on the side of the military vessel. It was a long drop, looking down the side of the ship. That was a pretty scary sight.
Michael Paul: We have specialised tools at our disposal in Gräfelfing and we can always order any spare parts we need at short notice. In Antarctica, it usually takes several weeks for a shipment to arrive. That made the planning stage in Germany even more important. There were plenty of sleepless nights for me. But in the end, everything worked out. Even though the crane parts were unloaded and reloaded multiple times, in the end, we were only missing four bolts, which the Chilean colleagues have kindly provided to us.
Charlie Zöllner: The conditions on site in Antarctica are like nothing else we’d ever experienced. Instead of working in an enclosed shop floor, we had to assemble the crane outdoors. Although we were actually pretty lucky with the weather, with temperatures around the freezing point, it’s a good thing we had our protective clothing with us because of the powerful Antarctic winds. We also fully appreciated the kindness of our fellow men when working on the island. For example, the Chilean military let us use a smaller crane during the assembly.
Charlie Zöllner: You just pray that after all the work, the crane will actually start up. You can imagine how relieved I was the moment I turned the key in the ignition and the crane started up immediately.
Michael Paul: Me too. I mean that shows that all our planning had really paid off. Looking back on it, I was especially impressed by how well everyone worked together, from the support we received from the German Aerospace Centre, to the expertise shared by Liebherr during the disassembly phase and then the help we received on site from the Chilean military. If it hadn’t been for that level of teamwork, a project like this would never have been feasible!
The German Aerospace Centre has been operating a polar research station on a small island around 30 kilometres off the northern tip of the Antarctic peninsula since 1991. The German Antarctic Receiving Station (GARS) O’Higgins receives satellite signals and Earth observation data via an antenna that was specially designed for operation in Antarctica.
The satellite signals and Earth observation data is analysed as part of multiple research projects and is fed into national and international databases. The data provides researchers with significant insights into how Antarctica is changing. This can also be used to help researchers learn more about the way the climate is changing worldwide.
Since 2010, the station has been operated by a team of four researchers all year round. For around two to three months each year, the researchers here must endure temperatures between -20°C and +8°C and wind forces of up to 200 kilometres per hour. The research station is divided into two units: one building houses the research facilities and the other contains the additional technical infrastructure. This infrastructure is essential because the station is operated autonomously and runs off its own power supply from diesel generators. There is also an osmosis installation for water treatment and a biological purification system. The infrastructure building needed an overhaul, so plans were made to renovate and extend it by 2022.
One of the challenges for the construction work is the lack of space on the island, which is only 300 x 200 metres in size. The German research station is also directly adjacent to the Base General Bernardo O'Higgins, a Chilean Antarctic Military Base. ‘It was absolutely critical for the German Aerospace Centre that the crane could be manoeuvred in these cramped conditions and that the construction site could be fully covered from a single location’, explains Minka St. James, who directed the project for Schmidbauer.
Customer service is also extremely important, even in Antarctica. It is crucial to use the short summer period as efficiently as possible because that is the only time of year in which construction work can be carried out and the transport routes are navigable. There is no time to waste. ‘That’s why we chose a Liebherr crane because, in the event of an emergency, an engineer can be sent to the research station from the Liebherr customer service centre in Chile’, Minka continues.
Once the crane was assembled, it was immediately shored up for the winter. All the test runs were successfully completed during the following Southern Hemisphere summer (December to March of 2019). The construction work to extend the research station kicked off officially in November 2019 and is expected to be completed in 2022.