Service as a high-wire act

430 metres above the abyss. Secured only by a climbing harness and a carabiner. Enveloped in thick fog. Icy wind whistles through the tower crane’s metal struts. Ivan Dikun lies face-down on a narrow metal walkway, so that he can check a sensor on the tower crane. “Up here, the constant wind and cold winter temperatures are our biggest challenges,” explains the service technician, who needs to keep a clear head even under time pressure. Today, the crane he is climbing on is shut down for scheduled routine maintenance. In an emergency situation, service work has to be performed as quickly as possible, so as not to hold up construction. Work on the new Saint Petersburg landmark can only continue once maintenance is completed.

At 462 metres, the Lakhta Tower is currently the tallest building in Europe. The skyscraper is located around ten kilometres from the city centre, directly by the Gulf of Finland. To build the high-rise, construction firm Renaissance Construction used three type 710 HC-L 32/64 Litronic tower cranes, as well as one 357 HC-L 12/24 Litronic. A hydraulic system allowed the cranes to climb up the external facade and inside of the tower. They were always one step ahead of the skyscraper.

We need your consent This YouTube video is provided by Google*. If you load the video, your data - including your IP address - is transmitted to Google and may be stored and processed by Google inter alia in the USA. We have no influence over further data processing by Google. By clicking on "Accept", you consent to the transmission of data to Google for this video in accordance with Art. 6 (1) (a) GDPR and at the same time expressly consent to the transfer of data to the USA in accordance with Art. 49 (1) (a) GDPR. If you no longer wish to consent to each YouTube video individually in the future and wish to be able to load the videos without this blocker, you can also select "Always accept YouTube" and thereby consent to the associated data transmissions and transfers to Google and to the USA for all other YouTube videos which you open on our website in the future. Please note that, in the opinion of the European Court of Justice, there does not currently exist an adequate level of data protection in line with EU standards in the USA, and at present we cannot provide suitable safeguards to protect your data and offset this shortcoming. Possible risks to you of data transfer to the USA are that access by state authorities cannot be excluded and that your data could be processed for reasons of national security, criminal prosecution or for other purposes in the public interest of the USA, possibly without you being informed separately and without enforceable rights and effective means of redress being available to you. You can withdraw consent that you have given at any time with future effect via the settings. For further information, please see our Data Protection Declaration and Google's Privacy Policy. *Google Ireland Limited, Gordon House, Barrow Street, Dublin 4, Irland; Mutterunternehmen: Google LLC, 1600 Amphitheatre Parkway, Mountain View, CA 94043, USA

We always need to think about our own safety and that of the other workers – no matter how high up we are..

Ivan Dikun

Under extreme conditions

Service technician Ivan Dikun made sure of it. At more than 400 metres up in the air, even standard tasks like checking limit switches and sensors are a high-wire act. For example when the service technician walks along the jib of the tower crane. Every few metres, he has to rehook the carabiner onto the guide rope that will catch him if he falls. “We always need to think about our own safety and that of the other workers – no matter how high up we are,” says Dikun. A dropped tool could be just as deadly as a fall.

Yet the real challenge on the Lakhta Tower is not its record-breaking height, it is the weather. “We are right next to sea and only about 1,000 kilometres from the Arctic Circle. Temperatures can get down to minus 32 °C here, with winds over 130 km/h,” Dikun says. Proper work clothes are essential to defy the weather. The tower cranes are designed to work under extreme conditions like these. But for safety reasons, maintenance tasks can only be carried out in winds of up to 72 km/h. So service technicians have to respond flexibly to weather conditions on site. This job calls for a steady hand, as well as a head for heights. “There is definitely a knack to changing oil in the wind, to make sure you don’t spill any,” the technician smiles. Apart from routine maintenance jobs like these, he and his colleagues at Tower Crane Customer Service assist distributors and customers with more challenging installations when required, or when the tower cranes have to be dismantled.

The biggest challenge was certainly the extreme building height. At 462 meters we need very powerful tower cranes.

Benedikt Bärtle

87 storeys in record time

Construction of the Lakhta Tower started in 2015. Work on the outside of the skyscraper was completed this year, and interior work is now underway – after a build time of only three years. It was a very tight schedule for a project of this size. Added to that, a mixed-use development with office space as well as sport and leisure facilities was built at the same time as the high-rise. Six more Liebherr tower cranes were used for this part of the project.

“Consequently, one special requirement we had was for technical support from Liebherr throughout all phases of our project,” says Rustam Doshchanov, project manager at Renaissance Construction. The construction company worked closely with Liebherr's own project department Tower Crane Solutions one year before construction began. „The earlier we come into the process, the better we will be able to adjust the crane concept to the construction site and to our customer in an individual way”, explains Benedikt Bärtle who is in charge of planning the project for Tower Crane Solutions.

During the planning phase the height of the building and the extreme weather conditions played a significant role. In order to guarantee rapid construction progress of the Lakhta Tower, very powerful tower cranes had to be employed. The decision was therefore made to use three 710 HC-L 32/64 Litronic tower cranes with a maximum working load of up to 64 tons and lifting speeds of up to 176 metres per minute. However, not only is the height of the building a challenge – so is its shape. The skyscraper resembles a gas flame tapering out at the top. The construction of the tower is unique with each floor being different. There can be thus no question of a standardized solution. The way the cranes climb up the building was individually adapted to the facade concept and the construction progress of the building.

We need your consent This YouTube video is provided by Google*. If you load the video, your data - including your IP address - is transmitted to Google and may be stored and processed by Google inter alia in the USA. We have no influence over further data processing by Google. By clicking on "Accept", you consent to the transmission of data to Google for this video in accordance with Art. 6 (1) (a) GDPR and at the same time expressly consent to the transfer of data to the USA in accordance with Art. 49 (1) (a) GDPR. If you no longer wish to consent to each YouTube video individually in the future and wish to be able to load the videos without this blocker, you can also select "Always accept YouTube" and thereby consent to the associated data transmissions and transfers to Google and to the USA for all other YouTube videos which you open on our website in the future. Please note that, in the opinion of the European Court of Justice, there does not currently exist an adequate level of data protection in line with EU standards in the USA, and at present we cannot provide suitable safeguards to protect your data and offset this shortcoming. Possible risks to you of data transfer to the USA are that access by state authorities cannot be excluded and that your data could be processed for reasons of national security, criminal prosecution or for other purposes in the public interest of the USA, possibly without you being informed separately and without enforceable rights and effective means of redress being available to you. You can withdraw consent that you have given at any time with future effect via the settings. For further information, please see our Data Protection Declaration and Google's Privacy Policy. *Google Ireland Limited, Gordon House, Barrow Street, Dublin 4, Irland; Mutterunternehmen: Google LLC, 1600 Amphitheatre Parkway, Mountain View, CA 94043, USA

Every construction phase is planned exactly. But in such large-scale projects it doesn’t only come down to that since not everything can be planned for. “We have to respond at short notice to the construction site and examine possible alternative approaches. For example when components have to be lifted that are heavier than originally planned,” says Bärtle.

The engineers from Biberach work closely together with Renaissance Construction and the service technicians of Tower Crane Customer Service on site, to enable a flexible and swift response. “Fast reaction times for repair and maintenance work are extremely important to us, because any hold-up in the crane’s operation would have delayed the construction work,” Doshchanov adds.

Ivan Dikun is aware of this too, as he completes his maintenance work about two hours later. “Dispatcher, come in. The check is complete, the crane can go back into operation.” Dikun speaks into his crackling radio then starts to descend. As he climbs down the final few metres inside the tower crane, it resumes its work on the tallest building in Europe.

This may be of interest to you

Up in the clouds

On Germany's biggest mountain, it's not just the views that are impressive: the crane technology has also reached new heights.

To the story

Tower cranes

Are you interested in the crane program of the Tower Cranes division? Click here for the product information.