Load capacity instead of dynamite

When explosions are not an option ...

“Hook up!”: Peter Stricker knows the LR 11000 like no one else. During the bridge demolition in Ulm, he was responsible for the precise operation of the large crane during the day.

Dimensions become clear: Dyneema slings are textile lifting and lashing systems that offer high load-bearing capacity whilst being lightweight. Compared with steel chains or wire ropes, they weigh only a fraction as much, making them much easier to handle on site. The load-balancing rocker, which ensures an even distribution of the load across all rope strands, can also be seen on the crane hook.

Crane ballast of 750 tonnes

Round the clock work was being carried out on the demolition of the bridge. Clearly visible at the rear of the crane: the retracted V-Frame with the split VarioTray ballast pallet.

Wide reach: With its 126-metre-long lattice boom, the crawler crane lifts bridge segments from a great distance above the railway tracks. It took around 40 heavy-haul transports and four days of set-up work before the crawler crane was able to begin its round-the-clock operation against the backdrop of the world-famous Ulm Minster.

Night shift: The saws worked their way through massive bridge structure. For crane operater Max Frei, this meant one thing above all else: the utmost concentration – often for several hours at a stretch.

Sophisticated slinging gear

Nibbling away: Immediately after dismantling, several demolition excavators set to work on the large reinforced concrete sections using their powerful grippers. The resulting construction waste was continuously removed to make way for the next section of the bridge.