News | 2015/09/23
According to the findings of the Liebherr crane experts sent to Saudi Arabia the LR 11350 was erected at the time of the accident with a boom length of approximately 190m, parked outside of the Grand Mosque and put out of operation. Previously it had sporadically been used for assembly works. In the late afternoon of 11 September 2015, during a strong thunderstorm and sandstorm with measured wind speeds of 80km/h (according to the CNN Weather Service) and 105km/h (wind recording of a Liebherr Tower Crane near the place of accident), heavy rain falls and a sudden drop in temperature by 20⁰C, the crawler crane was caught by the wind and tilted over the last support rollers of its crawler tracks.
The operating instructions of the LR 11350 and the associated "Wind Speed Charts" show that the crawler crane could not withstand such a high wind load and that the boom should have been lowered to the ground preventatively to avoid the tilting of the crawler crane.
In the meantime Liebherr has taken this very tragic accident in Mecca as reason to point out again to the operators of comparable Liebherr cranes worldwide the influences that wind has on cranes and to the unconditional compliance with the appropriate regulations mentioned in the operating instructions.
関連記事

2026/11/11
Press releases
AL.GIS. Sollevamenti S.r.l. boosts crane fleet with used LTM 1500-8.1 mobile crane from Liebherr
The Italian crane and heavy transport company AL.GIS. Sollevamenti S.r.l., based in Marcianise, near Naples, has expanded its crane fleet with a used Liebherr LTM 1500-8.1 mobile crane.

2026/11/10
Press releases
Liebherr supplies two new Betomix batching plants to Willaert Bouwmaterialen
With two new Liebherr Betomix 3.0 concrete batching plants, Willaert Bouwmaterialen is investing in the future of its ready-mix concrete production. Thanks to modern mixing technology, a sophisticated plant concept and optimally prepared site conditions, both plants were installed and commissioned in just 13 weeks. In addition to high production capacity, key factors in favour of the Liebherr plants were quality, reliability and the long-standing partnership.

2026/11/09
Press releases
On the road to the Champions League, Somalev adds ten Liebherr mobile cranes to its vehicle fleet
Somalev Cranes & Logistics, one of Morocco’s leading providers of heavy-lift technology and specialised transport, is making a strong statement: the company is expanding its vehicle fleet with ten state-of-the-art Liebherr mobile cranes.