Press releases | 2020-10-07
Liebherr Mining and VA Erzberg: an innovative partnership
- Trolley development contract signed at Bauma 2019
- Groundbreaking ceremony at VA Erzberg iron ore mine on September 29, 2020
- New 5 km trolley line for a fleet of six T 236 trucks, investment of 20 million euros
- VA Erzberg will save 3 million liters of diesel per year (equivalent to an overall mine fuel saving of 66%)
At Bauma 2019, VA Erzberg and Liebherr have concluded a development contract for a Trolley assist system for the T 236 (100t mining truck). Since then the iron ore mine has been testing the diesel-electric truck in Austria. The truck was modified to operate with an overhead line connected through a current collector with bars on a 500 m long test track. The groundbreaking ceremony for the extended 5 km trolley line took place on September 29, 2020.