Upgrade in the Alps

A once-in-a-century project between cliffs and ice

Solid: The enormous bases of the cranes were specially constructed for this project. The firmly anchored steel elements were designed to withstand even an avalanche. Ramon Goglione is one of the project’s construction managers.

Ramon Goglione, construction site management team

Power production without interruption

Curtain up on Lake Grimsel: At the start of construction work on the new dam in 2019, an LTM 1130-5.1 from Frutiger AG placed the containers for the construction workers’ accommodation.

Flooded: The almost hundred-year-old dam wall has been breached and will now stand in the water of the Alpine reservoir.

Michael Egger: “Here in the mountains, the construction period from May to October is very short. That’s why the entire logistics had to be organised very efficiently.”

“Really powerful and compact”

Steel and cliffs:The large luffing jib of the construction crane is suspended from heavy chains for dismantling.

Wall with expansion reserve