Press releases | 15/09/2015
LTR 1220 acts as counterweight for a Liebherr LR 1600/2 crawler crane
- Crane contractor Helling successfully uses auxiliary crane as ballast substitute on a 600-tonne crawler crane
- The coupled cranes move to the next site with a 150-meter boom
- Massive time savings and reduction in ballast transport
Crane contractor Helling based in Schwäbisch Gmünd in southern Germany provided an object lesson in the perfect use of crane equipment and synergies in large wind farms. A Liebherr LTR 1220 telescopic crawler crane which was at the site anyway for set-up work, was used by Helling as a counterweight for lowering and erecting the large LR 1600/2 crane rather than the usual ballast blocks. If the topography and farmers allow, the smaller crane can also be used to move the large crane to the next turbine.