Press releases | 23/09/2019
Liebherr LR 11350 and LR 11000 crawler cranes working in tandem
- Two Liebherr crawler cranes load a tunnel drilling machine
- The heaviest load in the history of the Rhine port of Kehl
- 1600 tonnes of ballast used
An industrial port was opened in May 1900 at Kehl in Baden-Württemberg. In May this year, this small border town on the German side of the River Rhine near Strasbourg was the venue for another impressive event – two crawler cranes moved cargo weighing around 900 tonnes onto a barge in a spectacular tandem hoist. “Never before in almost 120 years of its history has such a heavy item been handled at our Rhine port using cranes”, says Jürgen Preiss. And Preiss, a member of the port management team, knows exactly what he’s talking about. The load he is referring to was the core piece of a gigantic tunnel drilling machine built by Herrenknecht based in Schwanau, Baden-Württemberg. Two powerful crawler cranes from the Liebherr Plant in Ehingen were required to tackle this job.