Press releases | 20/08/2020
Complex night shift for six Liebherr cranes
- Crane contractor Nolte delivers top quality logistical service
- Six LTM mobile cranes install 71 metre skywalk
- Components of the pedestrian bridge suspended on crane hooks for 22 hours
Hanover-based Nolte Autokrane gave an impressive performance recently in its home city with a crane job that took a couple of days. A cantilever connection bridge measuring over 70 metres in length and made up of four components and a number of connecting elements had to be assembled in the air between two buildings of the newly erected headquarters of Continental AG (Conti). This difficult task posed a major challenge from both a crane and logistics point of view.