The first job awaiting the new Liebherr LR 1750/2 crawler crane operated by Fanger Kran AG was a demanding one in central Switzerland near Lucerne. The crane had to handle a gross load of around 270 tonnes to replace a 30-metre cylinder. In a very constricted space in the production plant of a manufacturer of wooden materials, the job was only possible by moving the crane whilst it held the load.
With its purchase of this new powerful 750-tonne class crawler crane, Fanger Kran AG opened a whole new chapter in the history of lifting equipment stationed in Switzerland. At the same time the family-run company remained true to its tradition – when it purchased a Liebherr LR 1400 crane in 1997, Fanger also presented the most powerful crawler crane in Switzerland at the time. It was used to complete the hoisting work for many large Swiss projects such as bridge and tunnel construction work. The new machine will now replace this old crane which is almost twenty years old.
The Fanger team led by Project Manager Josef Waser was confronted with a tricky task for the crane's first job. An enormous cylinder in the production plant of a wooden materials manufacturer had to be replaced in difficult conditions and under time pressure. Because the plant's production had to be stopped for the duration of the work, for the customer it was extremely important to have the job completed quickly and smoothly.
Before the old cylinder was hoisted out of the plant, an auxiliary platform first had to be hoisted in and installed. After the steel drum had been pulled out of the plant onto this platform, the hanging gear with a weight of around 30 tonnes was attached to the load. To hoist the gigantic tube out of the production plant, the radius of 31 metre had to be reduced slightly and a total of 270 tonnes had to be hoisted to an initial hook height of 64 metres. Only in this position the crawler gear could be carefully set in motion. Whilst the crane completed the distance of around 15 metres, the massive steel cylinder was swung over silos and factory buildings and then deposited on the ground.
The LR 1750/2 crawler crane was fitted with the remarkable figure of 575 tonnes of ballast for this job and for the installation of the new component two days later. The suspended ballast on the derrick boom alone weighed 360 tonnes, which is close to maximum.
You might also be interested in

11/04/2026
Press releases
MK Week in Italy: Customers experience the Liebherr MK 88 Plus mobile construction crane in action
From 28 September to 2 October, Liebherr Italia S.p.A. organised an MK Week in Monfalcone for customers from Italy. The centrepiece of the five-day event was a used MK 88 Plus mobile construction crane.

11/03/2026
Press releases
Liebherr LTM 1650-8.1 in a spectacular working position
A Liebherr LTM 1650-8.1 mobile crane from MSG Krandienst GmbH was used in Lauffen am Neckar to completely dismantle a dilapidated arch bridge dating from 1951.

11/02/2026
Press releases
Schmidbauer invests in 17 new Liebherr cranes
Schmidbauer GmbH & Co. KG is making a major investment in the modernisation and expansion of its crane fleet and has ordered a total of 17 new cranes from Liebherr.