For around one year the IJsselmeer (Lake IJssel) in the north of the Netherlands was the scene of an unusual job for a LR 11350. The crawler crane erected the complete "Westermeerwind" wind farm from a massive jack-up platform. Crane contractor Mammoet completed the last of the 48 Siemens wind turbines with a hub height of 95 metres on schedule in February.
During the initial phase of the project from March 2015, gigantic foundation piles with a diameter of five metres had to be driven 25 metres into the bed of the lake. The monopiles measured up to 40 metres in length and weighed 300 tonnes. The Liebherr crawler crane position these massive tubes precisely using a radius of 36 metres.
All the foundation piles had been inserted by the end of May. After the technical equipment had been installed in the foundations and the turbines connected to the network during the months of summer, work was started in September on installing the tower segments, gondolas and rotor stars, the final phase of the project.
Large transport pontoons, each laden with the two-piece turbine tower and a gondola, were moved by tugs from the Port of Amsterdam to the construction site 60 kilometres away. The two tower sections measuring 50 and 40 metres in height were transported upright which enabled the LR 11350 to hoist and assemble the components without an auxiliary crane. The lower tower segment was the largest load for the crawler crane, weighing in at 150 tonnes. However the support of a small floating crane was required for lifting and tipping the rotor star. The rotors have a diameter of 108 metres and were assembled on the opposite coast of the IJsselmeer and then transported to the site on Arches.

10/06/2026
Press releases
A step up: Schweri opts for new Liebherr LTM 1300-6.4 mobile crane
Schweri Autokranbetriebe GmbH & Co. KG is putting an LTM 1300-6.4 into service. With this 300-tonne crane, the company is increasing the lifting capacity of its fleet and responds to increasing demands in wind power, industrial and precast concrete installation projects.

10/01/2026
Press releases
Pipe Mikado at the cement works: Liebherr LTM 1650-8.1 moves heavy loads in confined spaces
At the Holcim cement plant in Dotternhausen, a Liebherr LTM 1650-8.1 mobile crane from Wiesbauer GmbH & Co. KG mastered a challenging installation lift: two pipes, each weighing 33 tonnes, had to be hoisted into a new flue gas cleaning plant between existing pipes.

09/30/2026
Press releases
Permit-free from south to north: new Liebherr LTM 1055-3.3 mobile crane for Schlamann-Autokrane GmbH
The LTM 1055-3.3 is the second of four new Liebherr mobile cranes ordered by Schlamann-Autokrane GmbH this year. The new 55-tonne crane is the lightest 3-axle all-terrain crane on the market: it travelled from the Liebherr plant in Ehingen, Upper Swabia, to Nienburg in Lower Saxony without the need for complex authorisation procedures.