Crane and heavy load logistics contractor Maxikraft used two large Liebherr mobile cranes in July to load two condensers and a turbine from low loaders into ships in Dresden's Alberthafen dock. The challenge was that the giant components had to be moved in tandem hoists between the LTM 1500-8.1 and the LTM 1750-9.1 before they could be lowered into the dock basin.
The turbine was the heaviest single component at 214 tonnes, with the LTM 1500-8.1 handling a load of 102 tonnes and the LTM 1750-9.1 112 tonnes. The cranes could only use a maximum of 80 percent of their lifting capacity with the tandem hoists. The turbine was supplied by the Siemens Plant in Görlitz where the company has the headquarters of its global steam turbine business. The two condensers came from a plant in the Görlitz suburb of Hagenwerder. The massive system components will now be transported to Copenhagen by water, where they will then be used in a new waste incineration plant.
Možná vás také zajímá

21. 10. 2026
Press releases
Liebherr electrifies hydraulic construction project with unplugged crawler crane
For the refurbishment of the Brouwer sluice lock complex on the Brouwersdam in the Netherlands, the company De Klerk Werkendam is relying on Liebherr’s battery-powered LR 1130.1 unplugged crawler crane. As part of this, the 50-year-old sheet pile structures are being replaced; these play a key role in regulating the flow of water between the North Sea and the Grevelingenmeer.

19. 10. 2026
Press releases
Liebherr LR 11350 erects the world’s tallest wind turbine
At the end of September, what is now the world’s tallest wind turbine was completed. A Liebherr LR 11350 crawler crane from Schmidbauer GmbH & Co. KG was used in the construction of the prototype of the so-called GICON high-altitude wind turbine in Lusatia, Brandenburg.

16. 10. 2026
Press releases
A historic suspension railway carriage is once again gliding through Wuppertal: using a Liebherr LTM 1450-8.1 mobile crane, Franz Bracht Kran-Vermietung GmbH lifted carriage 76, weighing around seven tonnes, into Wuppertal Central Station. Given the limited space available, precise operational planning and modern mobile crane technology were crucial.