The motorway section of the A3 between Cologne-Mülheim and Leverkusen is being expanded to eight lanes. However, since the old motorway bridges are not long enough for the expansion, new bridges are needed. As a temporary solution during the construction work, a Liebherr LTM 1300-6.2 mobile crane was used by the company HKV Schmitz + Partner to erect a makeshift bridge overnight.
"The 300-tonne crane provides strong lifting capacities and was perfectly suited for this application," said Michael Schmitz, Technical Director at HKV. The LTM 1300-6.2 was delivered to HKV in April this year and is equipped with Liebherr's innovative VarioBase® support system which provides increased safety and higher lifting capacities.
The temporary bridge was delivered in four parts by semi low-loaders; the heaviest single piece weighed in at 41 tonnes and the length of the longest section was 24 metres. The LTM 1300-6.2 unloaded the sections from the low-loaders before placing them onto prepared foundations, where they were erected to form the temporary bridge.

2026. 10. 13.
Press releases
Boosting performance for wind power expansion: Gertzen retrofits the LR 1800-1.0 with the X3 system
Gertzen Kranlogistik GmbH & Co. KG has retrofitted its Liebherr LR 1800-1.0 crawler crane with the X3 boom system. With this upgrade, the company is significantly expanding its range of services in the wind energy sector.

2026. 10. 08.
Press releases
THW builds Danube bridge using four Liebherr LTC 1050-3.1 cranes
In Tuttlingen, southern Germany, four small Liebherr cranes have achieved great things: as a temporary replacement for a Danube bridge due for demolition, the LTC 1050-3.1 compact cranes erected a 70-metre-long river crossing as part of a civil defence exercise.

2026. 10. 07.
Press releases
Replacing the European Parliament’s air-conditioning system in Luxembourg required a long reach, precise planning and meticulously coordinated logistics. A Liebherr LTM 1650-8.1 mobile crane from STEIL Kranarbeiten in Trier lifted six old components from the roof and installed the new units.