News | 2015. 09. 23.
News | 2015. 09. 23.
According to the findings of the Liebherr crane experts sent to Saudi Arabia the LR 11350 was erected at the time of the accident with a boom length of approximately 190m, parked outside of the Grand Mosque and put out of operation. Previously it had sporadically been used for assembly works. In the late afternoon of 11 September 2015, during a strong thunderstorm and sandstorm with measured wind speeds of 80km/h (according to the CNN Weather Service) and 105km/h (wind recording of a Liebherr Tower Crane near the place of accident), heavy rain falls and a sudden drop in temperature by 20⁰C, the crawler crane was caught by the wind and tilted over the last support rollers of its crawler tracks.
The operating instructions of the LR 11350 and the associated "Wind Speed Charts" show that the crawler crane could not withstand such a high wind load and that the boom should have been lowered to the ground preventatively to avoid the tilting of the crawler crane.
In the meantime Liebherr has taken this very tragic accident in Mecca as reason to point out again to the operators of comparable Liebherr cranes worldwide the influences that wind has on cranes and to the unconditional compliance with the appropriate regulations mentioned in the operating instructions.

2026. 10. 08.
Press releases
Innovative solutions for the next generation of business jets: Liebherr at NBAA-BACE 2026
At NBAA-BACE, taking place from October 20 to 22, 2026, in Las Vegas, Nevada (USA), Liebherr-Aerospace will showcase its cutting-edge innovations for the business jet market at booth no. 3555. Visitors can discover state-of-the-art systems and components, including a nose landing gear, an air-conditioning pack and modular electro-mechanical actuators.

2026. 10. 08.
Press releases
Three Liebherr flat-top cranes support the transformation of Milan's Bovisa gasometers
Two early twentieth century gasometers in the Bovisa district of Milan are being redeveloped into a new innovation campus for Politecnico di Milano, based on a master plan by architect Renzo Piano. Since March 2025, three Liebherr flat-top cranes have covered the entire construction site, handling lifting and material handling work across the project.

2026. 10. 08.
Press releases
THW builds Danube bridge using four Liebherr LTC 1050-3.1 cranes
In Tuttlingen, southern Germany, four small Liebherr cranes have achieved great things: as a temporary replacement for a Danube bridge due for demolition, the LTC 1050-3.1 compact cranes erected a 70-metre-long river crossing as part of a civil defence exercise.