Five questions that show why planning a tower crane deployment is more complex than you might think

Max Widder, Head of Project Planning, Tower Crane Solutions bei Liebherr.

1. Why isn't the strongest available crane simply enough for a record-breaking structure?

The Fehmarnbelt Tunnel between Denmark and Germany: at around 18 kilometres, the longest immersed tunnel in the world. More than 20 Liebherr tower cranes are in operation here, many of them rail-mounted.

2. Over 50 cranes at Istanbul Airport, a two tower cranes at the Sagrada Família: which projects present Tower Crane Solutions with the greater challenge?

Sagrada Família in Barcelona: a Liebherr 710 HC-L 32-64 Litronic with a load capacity of 64 tonnes is supporting the completion of the Tower of Jesus Christ, which has now reached its final height of 172 metres.

3. Liebherr cranes supported the completion of the Sagrada Família’s Tower of Jesus Christ, one of the most famous buildings in the world. What makes this project so special for you personally?

The Çanakkale Bridge in Türkiye: with a span of 2,023 metres, the longest suspension bridge in the world. Two Liebherr 357 HC-L 12/24 Litronic luffing jib cranes were used on the pylons, each erected at a height of 318 metres.

4. How does crane planning actually come together, and how does TCS provide support throughout the entire project?

Filstal Bridge on the Wendlingen–Ulm high-speed line: four cranes from the EC-H series, including a 630 EC-H 40 Litronic, were deployed on the roughly 500-metre-long, 85-metre-high bridge.

5. What sets Tower Crane Solutions apart from a classic external planning consultancy?

Video

Contacts

Shannon Korff, Marketing Specialist
Shannon Korff
Marketing Specialist
Liebherr-Werk Biberach GmbH Memminger Straße 120 88400 Biberach an der Riß Germany

Cela pourrait également vous intéresser

  • Three Liebherr flat-top cranes support the transformation of Milan's Bovisa gasometers

    08/10/2026

    Press releases

    Three Liebherr flat-top cranes support the transformation of Milan's Bovisa gasometers

    Two early twentieth century gasometers in the Bovisa district of Milan are being redeveloped into a new innovation campus for Politecnico di Milano, based on a master plan by architect Renzo Piano. Since March 2025, three Liebherr flat-top cranes have covered the entire construction site, handling lifting and material handling work across the project.

  • Une plus grande confiance grâce à de nouvelles expériences : Liebherr prolonge la durée de vie des câbles en fibres

    02/10/2026

    Communiqués de presse

    Une plus grande confiance grâce à de nouvelles expériences : Liebherr prolonge la durée de vie des câbles en fibres

    Liebherr augmente la durée de vie totale de ses câbles en fibres de 14 à 16 ans, leur durée d’utilisation effective peut atteindre 12 ans. Ces conclusions s’appuient sur des essais de vieillissement menés sur plusieurs années sur des bancs d’essai et sur des analyses de câbles utilisés sur le terrain. Cette règle s’applique automatiquement à tous les câbles, qu’ils soient neufs ou déjà en service.

  • Considerate and flexible: two Liebherr NC-B cranes at work in Sai Kung

    10/09/2026

    Press releases

    Considerate and flexible: two Liebherr NC-B cranes at work in Sai Kung

    A new residential development is under construction in Ho Chung, Sai Kung. Foundation and excavation and lateral support works have been underway since December 2024 and are expected to continue until end of 2026. Two Liebherr NC-B 12-70 tower cranes are handling material logistics on the confined site.