Press releases | 01/18/2021 Digitalization in deep foundation work: The positioning system LIPOS ® supports continuous flight auger drilling

Every building stands on a solid foundation that bears the whole weight. However, when the ground below is too soft or unstable, qualified deep foundation specialists come into play in order to provide the required ground bearing capacity. With the LIPOS system, Liebherr equips the deep foundation specialists with a tool that simplifies the task in various ways.

A perfect symbiosis: From the concrete mixer, to the concrete pump and up to the drilling rig - all equipment is made by Liebherr.

Single image, web (389 KB)

The LIPOS antennae are mounted directly on the leader and allow for centimetre precision in positioning.

Single image, web (206 KB)

Test measurements can be carried out quickly and easily using the Rover Rod.

Single image, web (346 KB)

The exact position of the Liebherr machine is constantly displayed on the additional LIPOS monitor in the cab.

Single image, web (264 KB)

The Burgenland Hospital Association, KRAGES, is building a general hospital in Oberwart, Austria. The new building, in direct vicinity to the existing hospital, shall guarantee excellent medical, nursing and therapeutic care in the region. In order to avoid subsequent settlement and damage to the new building, the available land requires substantial foundation work before it can support a whole hospital.

Züblin Spezialtiefbau Ges.m.b.H. equips its first Liebherr drilling rig for the digital age

The company Züblin Spezialtiefbau Ges.m.b.H. was contracted to install 1,310 piles in an area of 23.000 m² for the foundation of the complete new building. All piles have a diameter of 630 mm and are being installed using the CFA (continuous flight auger) method. The maximum depth of the foundation piles is 16 m. Initially, it was assumed that a construction period of approximately 4 months would be required to complete more than 1000 piles. To complete the task, Züblin Spezialtiefbau is using a Liebherr drilling rig type LB 28, which has been equipped with the positioning system LIPOS for the first time. The LB 28 is supported on site by a Liebherr concrete pump type THS 110, which ensures that the delivered concrete is immediately pumped to the required location.

All drilling points can be quickly selected and the machine positioned

Once the complete building ground was exactly measured and the precise position of each single pile was identified, the gathered data could be transferred as a digital drilling plan to the LIPOS positioning system in the Liebherr machine in no time. Jobsite data and pile lists for work to be carried out are transferred to the machine when the drilling list is uploaded. The operator sees his position with centimetre precision at all times thanks to an additional monitor in the cabin. The LB 28 can be manoeuvred with ease to each of the 1,310 drilling points without the need of any iron stakes or colour markings for orientation. The operator no longer has to watch out for ground markings or the concrete hose. He can concentrate on important things, is more flexible and independent, and therefore, quicker in handling the drilling rig. Furthermore, the system simplifies the positioning of jobsite equipment. The concrete pump, the reinforcements, as well as other tools and material can be optimally positioned around the drilling rig.

Productivity results from the combination of high performance machine technology and sophisticated assistance systems

An above-average daily drilling performance is achieved using the LB 28 and the construction work could be completed earlier than planned, actually after only 3 months. One reason, in addition to the reliable Liebherr construction machine, is the extremely productive working method. The LIPOS positioning system plays a decisive role here. Without this system the drilling points would have to be newly measured, drawn and marked at least three times a day. An enormous additional effort which is completely eliminated with the help of LIPOS. All jobsite personnel has a clear overview at all times of exactly where the piles are, which piles are already completed and which still have to be done. One thing is clear for the site manager Harald Fugger following his experience on the jobsite in Oberwart, “The LIPOS positioning system is ideally suited for completing jobsites, especially using the CFA method. It has proven itself well on the jobsite and makes working processes easier allowing continuous real time control and monitoring. Quality management is considerably improved through the automatic recording of the processes. The LIPOS system is basically self-explanatory for the operator and convinces through easy handling.”

Downloads

Here you will find the press release and images for download.

Presseinformation Deutsch PDF (390 KB)
Press Information English PDF (389 KB)

Video

We need your consent This video is provided by Google*. When you load this video, your data, including your IP address, is transmitted to Google, and may be stored and processed by Google, also for its own purposes, outside the EU or the EEA and thus in a third country, in particular in the USA**. We have no influence on further data processing by Google. By clicking on “ACCEPT”, you consent to the data transmission to Google for this video pursuant to Art. 6 para. 1 point a GDPR. If you do not want to consent to each YouTube video individually in the future and want to be able to load them without this blocker, you can also select “Always accept YouTube videos” and thus also consent to the respectively associated data transmissions to Google for all other YouTube videos that you will access on our website in the future. You can withdraw given consents at any time with effect for the future and thus prevent the further transmission of your data by deselecting the respective service under “Miscellaneous services (optional)” in the settingslater also accessible via the “Privacy Settings” in the footer of our website). For further information, please refer to Data Protection Declaration and the Google Privacy Policy. * Google Ireland Limited, Gordon House, Barrow Street, Dublin 4, Ireland; parent company: Google LLC, 1600 Amphitheatre Parkway, Mountain View, CA 94043, USA
** Note: The data transfer to the USA associated with the data transmission to Google takes place on the basis of the European Commission’s adequacy decision of 10 July 2023 (EU-U.S. Data Privacy Framework).