Sweden’s first Fibre crane: ultra-light assembly in tight conditions

Construction of the 23-storey “Sickla Stationshus” is under way in Stockholm. A Liebherr 370 EC-B Fibre tower crane has been erected for this project – the first crane of its kind in Sweden. It features a high-tensile fibre rope that offers up to 20 percent more jib head load capacity and has a freestanding hook height of more than 100 m.

Daniele Solito, part owner of Binsell, explains, “The challenges of this site included the erection of two freestanding cranes, 107 and 76 m high, in a very confined space. Although tie-ins would have been normal at this height, guying wasn’t used as the customer wished to avoid holes in the façade. To protect the adjacent railway track area, slewing and trolley travel limitations were put in place as well as anti-collision systems.”

Binsell rents mobile cranes, tower cranes and crane trucks. With over 120 mobile cranes and tower cranes, Binsell Stockholm is Stockholm's largest supplier of cranes. The company works together closely with Alfab Service AB. Based in Västerås, Alfab Service AB has been a reliable dealer for Liebherr mobile cranes and tower cranes in Sweden since 1981.

Total enthusiasm

Anders Andersson, service technician at Binsell Sverige AB, is enthusiastic about his work with the 370 EC-B Fibre, “It’s the first time that we’re using a Fibre crane and, I have to say, it’s amazingly easy to handle. Not just because the steel ropes we usually work with are heavier but also because assembly is much easier. Plus, the fibre rope is really light. We’re having a great time at work and our assembly team is fantastic. I like working so high up as well.”

Good planning is the key to success

The crane was erected over the course of a long weekend. This short window of time meant that the assembly had to be planned with precision. A specific configuration was needed to achieve the required freestanding hook height of over 107 m. The 370 EC-B Fibre stands on 3150 HC foundation anchors, which are anchored into rock. Liebherr’s modular design system makes it possible to combine 1000 HC, 630 EC-H, 500 C and 256 HC tower sections to achieve the specified freestanding hook height. The foundation only requires an area of 5 x 5 metres. To avoid the potential problem of high winds preventing climbing, the crane was assembled to its final hook height. A 280 EC-H crane was also in use for the construction of the building’s lower floors.

The “Stationshus” is being developed by the Swedish real estate company Atrium Ljungberg. The office building with shopping centre is located directly next to the “Sickla” train station, which is a key public transport connection.

Video

Construction of the 23-storey “Sickla Stationshus” is under way in Stockholm. A Liebherr 370 EC-B Fibre tower crane has been erected for this project – the first crane of its kind in Sweden
We need your consent This video is provided by Google*. When you load this video, your data, including your IP address, is transmitted to Google, and may be stored and processed by Google, also for its own purposes, outside the EU or the EEA and thus in a third country, in particular in the USA**. We have no influence on further data processing by Google. By clicking on “ACCEPT”, you consent to the data transmission to Google for this video pursuant to Art. 6 para. 1 point a GDPR. If you do not want to consent to each YouTube video individually in the future and want to be able to load them without this blocker, you can also select “Always accept YouTube videos” and thus also consent to the respectively associated data transmissions to Google for all other YouTube videos that you will access on our website in the future. You can withdraw given consents at any time with effect for the future and thus prevent the further transmission of your data by deselecting the respective service under “Miscellaneous services (optional)” in the settings later also accessible via the “Privacy Settings” in the footer of our website). For further information, please refer to Data Protection Declaration and the Google Privacy Policy. * Google Ireland Limited, Gordon House, Barrow Street, Dublin 4, Ireland; parent company: Google LLC, 1600 Amphitheatre Parkway, Mountain View, CA 94043, USA
** Note: The data transfer to the USA associated with the data transmission to Google takes place on the basis of the European Commission’s adequacy decision of 10 July 2023 (EU-U.S. Data Privacy Framework).
Watch the video to learn more about the construction site’s features: Open video
Construction of the 23-storey “Sickla Stationshus” is under way in Stockholm. A Liebherr 370 EC-B Fibre tower crane has been erected for this project – the first crane of its kind in Sweden
We need your consent This video is provided by Google*. When you load this video, your data, including your IP address, is transmitted to Google, and may be stored and processed by Google, also for its own purposes, outside the EU or the EEA and thus in a third country, in particular in the USA**. We have no influence on further data processing by Google. By clicking on “ACCEPT”, you consent to the data transmission to Google for this video pursuant to Art. 6 para. 1 point a GDPR. If you do not want to consent to each YouTube video individually in the future and want to be able to load them without this blocker, you can also select “Always accept YouTube videos” and thus also consent to the respectively associated data transmissions to Google for all other YouTube videos that you will access on our website in the future. You can withdraw given consents at any time with effect for the future and thus prevent the further transmission of your data by deselecting the respective service under “Miscellaneous services (optional)” in the settings later also accessible via the “Privacy Settings” in the footer of our website). For further information, please refer to Data Protection Declaration and the Google Privacy Policy. * Google Ireland Limited, Gordon House, Barrow Street, Dublin 4, Ireland; parent company: Google LLC, 1600 Amphitheatre Parkway, Mountain View, CA 94043, USA
** Note: The data transfer to the USA associated with the data transmission to Google takes place on the basis of the European Commission’s adequacy decision of 10 July 2023 (EU-U.S. Data Privacy Framework).

EC-B Flat-Top cranes at a glance

The Flat-Top EC-B cranes feature simple, practical erection. Fitted with powerful drive units, these Flat-Top cranes deliver bespoke solutions. Product overview of Flat-Top cranes

Tower cranes sales and service

Our customers can rely on a worldwide sales and service network. Look for the contact you need here. Find a service partner

Tower Crane Solutions

Low cost solutions

The team at Tower Crane Solutions can offer advice when planning the lowest cost solution specific to your project. Tower Crane Solutions