18 Liebherr mobile cranes reinforce power line

Only the LTM 1650-8.1 from AKM had to lift “its” power mast all on its own. On the other three construction sites, the large cranes tackled the project with a tandem lift. Here, smaller Liebherr mobile cranes erect a completely new base for the high-voltage mast.

A back-breaking job: The installation work on the individual masts took up to three days. Maximum concentration was required from the crane operators and the 40 or so people working at height in their climbing harnesses.

Around 20,000 plates were put down on the muddy fields in order to create site access roads and secure parking spaces for the cranes.

Parallel down to the last detail: From the ballast and the Y-guying to the telescopic extension and the mighty luffing jib, the two cranes from the Austrian companies Felbermayr and Prangl had virtually identical specifications. Two yellow LTM cranes from the AKM partner Klema took care of the setup work on the large cranes and the assembly work on the power mast.

Two nights on the hook

Project manager: AKM Managing Director Sven Bauer planned and took responsibility for the logistically challenging crane mission involving 18 Liebherr cranes.

20,000 steel and aluminium plates ensure solid foundations

Midnight idyll: The picture shows the two cranes from MSG Krandienst and Wiesbauer. They are supporting the 85-tonne load while ground fog rises during the evening.

Liebherr service was guaranteed