Press releases | 15/10/2026

Liebherr overcomes access restrictions to lift a Derrick crane onto a Paris high-rise roof

"We do not start with a crane, we start with a challenge. In this case, the challenge lay in lifting several tonnes of material onto a high-rise rooftop in the heart of Paris. Restrictions on access and load-bearing capacity ruled out conventional lifting solutions. Only after analysing those constraints did, we conclude that a derrick crane was the right answer,”
explains Jochen Wille, Project Manager Tower Crane Solutions, Liebherr.

Video

Contacts

Shannon Korff, Marketing Specialist
Shannon Korff
Marketing Specialist
Liebherr-Werk Biberach GmbH Memminger Straße 120 88400 Biberach an der Riß Germany