For around one year the IJsselmeer (Lake IJssel) in the north of the Netherlands was the scene of an unusual job for a LR 11350. The crawler crane erected the complete "Westermeerwind" wind farm from a massive jack-up platform. Crane contractor Mammoet completed the last of the 48 Siemens wind turbines with a hub height of 95 metres on schedule in February.
During the initial phase of the project from March 2015, gigantic foundation piles with a diameter of five metres had to be driven 25 metres into the bed of the lake. The monopiles measured up to 40 metres in length and weighed 300 tonnes. The Liebherr crawler crane position these massive tubes precisely using a radius of 36 metres.
All the foundation piles had been inserted by the end of May. After the technical equipment had been installed in the foundations and the turbines connected to the network during the months of summer, work was started in September on installing the tower segments, gondolas and rotor stars, the final phase of the project.
Large transport pontoons, each laden with the two-piece turbine tower and a gondola, were moved by tugs from the Port of Amsterdam to the construction site 60 kilometres away. The two tower sections measuring 50 and 40 metres in height were transported upright which enabled the LR 11350 to hoist and assemble the components without an auxiliary crane. The lower tower segment was the largest load for the crawler crane, weighing in at 150 tonnes. However the support of a small floating crane was required for lifting and tipping the rotor star. The rotors have a diameter of 108 metres and were assembled on the opposite coast of the IJsselmeer and then transported to the site on Arches.

08/09/2026
Press releases
For the construction sites of tomorrow: Hiap Heng enters the mobile construction crane market
On 2. August, the Hiap Heng Group took delivery of its first Liebherr mobile construction crane. With the MK 88-4.1E, the company is expanding its fleet with an efficient lifting solution for construction sites with limited space. The crane combines versatility with high performance and enables fast, low-emission operations on urban construction projects.

04/09/2026
Press releases
Between two six-storey residential blocks in Uppsala (Sweden), a Liebherr mobile construction crane had to move large sections of a canopy from one building to the next.

31/08/2026
Press releases
Centro Oeste takes delivery of Brazil’s first Liebherr LTM 1300-6.4 mobile crane
Centro Oeste is the first company in Brazil to put a Liebherr LTM 1300-6.4 mobile crane equipped with the LICCON3 control system into operation. The 300-metric-tonne crane, with its 90-metre telescopic boom, expands the company’s capabilities for demanding industrial, infrastructure and energy projects.